Water Plant Updates

The Nanostone prototype for the pilot program at the Marlin Water plant was delivered and installed Jan. 17. Engineers will conduct the pilot for 30 days. They will have an additional 10 days for TCEQ performance review measures. If cleared after 40 days, the Marlin water plant will be retrofitted with new Nanostone filters that will carry a guaranteed warranty of 20 years against failure.